SRST-1Fieldale Recreation Center Grounds:

Earlier this year revisions were made to the original conceptual design based on current and future uses.  These revisions were incorporated over the last couple months bringing the design work to 90% complete.

Next steps:

  • Review and comment on 90% design
  • Design team utilizes feedback to make final changes
  • Preparation of bid package by early summer
  • Bidding projected mid-to-late summer

 

MarshallWayConceptuals-1Business District Building Facades:

Design work is 90% complete.  Proposed façade improvements and applications have been sent to business owners for their review and comment.

Next steps:

  • Business owners submit applications and comments allowing the County to move forward to bidding.
  • Bidding is projected this summer